Files
EVOLV/.claude/skills/evolv-commissioning-validation/SKILL.md
znetsixe d4e72f280e docs: retire repo-mem MCP, migrate skills to .claude/skills, audit fixes
- Delete .mcp.json + .claude/rules/repo-mem.md; drop .repo-mem from .gitignore
- Remove repo-mem / substrate_score / repo_search references from all .md
- Move 15 EVOLV skills from .agents/skills/ to .claude/skills/ so they are
  auto-discovered by the Claude Code harness and invokable via the Skill tool
- Retire .agents/skills/evolv-orchestrator (duplicate of the subagent at
  .claude/agents/evolv-orchestrator.md); orchestrator lives as a subagent only
- Drop OpenAI-format agent yaml metadata from each skill (not needed for CC)
- Update CLAUDE.md, CONTRACTS.md, AGENTS.md to point at the new locations and
  disambiguate skills (.claude/skills/) vs subagents (.claude/agents/)
- Fix CLAUDE.md tick-loop wording (opt-in per-node, not a fixed 1000ms)
- Widen .claude/rules/ paths frontmatter so node-architecture and telemetry
  rules trigger on more relevant files; add frontmatter to flow-layout rule
- Bump CONTRACTS.md review date to 2026-05-19; add step 7 to the contract-
  change workflow (review example flows when topic usage changes)
- Bump nodes/generalFunctions pin (Home.md substrate_score reference removed)

Co-Authored-By: Claude Opus 4.7 (1M context) <noreply@anthropic.com>
2026-05-19 09:30:49 +02:00

2.0 KiB

name, description
name description
evolv-commissioning-validation Plan and verify EVOLV commissioning readiness. Use when defining FAT/SAT test plans, acceptance criteria, loop checks, simulation-to-field validation, startup sequencing evidence, and rollout gates for operational deployment.

EVOLV Commissioning Validation

Mission

Convert implementation changes into deployment-ready evidence with clear acceptance gates.

Harness Execution Contract

  • Start from impacted contracts, modes, and site-operational constraints.
  • Define invariants before edits:
    • validation criteria are measurable and reproducible
    • startup and failover behavior is proven, not assumed
    • rollback path is explicit
  • Produce evidence artifacts tied to concrete tests/checks.

Scope

  • Cross-node behavior spanning control, measurement, and integrations
  • Test plans and validation docs under repository documentation paths
  • Node-level suites where commissioning evidence is derived

Workflow

  1. Build FAT/SAT matrix from impacted contracts and risk areas.
  2. Define pass/fail criteria and required instrumentation visibility.
  3. Execute or script reproducible validation checks.
  4. Capture evidence with timestamps, commands, and outcomes.
  5. Define rollout gates and rollback triggers.

Standards

  • Prefer deterministic replayable checks over ad-hoc validation.
  • Include negative-path and recovery-path tests.
  • Tie each acceptance criterion to a concrete artifact.
  • Keep operator handoff notes concise and actionable.

Test Expectations

Cover:

  • startup/shutdown commissioning sequences
  • failover and reconnect scenarios
  • alarm/interlock behavior under commissioning cases
  • post-deploy smoke checks and regression shortlist

Deliverables

Return:

  • FAT/SAT-style validation matrix
  • executed evidence summary
  • go/no-go risks and mitigations
  • rollback plan and monitoring checklist

Decision interview triggers:

  • reduced commissioning scope under schedule pressure
  • acceptance of unresolved high-severity risks
  • rollout sequencing choices with operational impact